B.C. coal miner seeks to scale back water treatment in polluted Elk Valley
The company's amended plan eliminates three planned treatment plants and six expansions of existing ones.
Elk Valley Resources, the largest coal miner in British Columbia, wants to reduce the number of new water treatment facilities it will build in the Elk Valley. The company's amended plan would eliminate three planned plants and six expansions of existing ones in the watershed, which has some of the world's highest selenium pollution. Selenium is a mineral that becomes toxic to fish and other aquatic life at high concentrations. The move comes as the company, a subsidiary of Glencore, is seeking to expand its mining operations in the region.
Critics in Canada and the United States say the company is backing away from its cleanup commitments. Elk Valley Resources spokesperson Chris Stannell did not confirm the specific reductions. "Selenium concentrations downstream of [Elk Valley Resources'] operations have declined to levels last observed approximately a decade ago, and that trend is expected to continue," Stannell wrote in an email. He said the changes to the treatment plan "do not directly equate to less treated water."
Derf Johnson, deputy director of the Montana Environmental Information Center, said Glencore is effectively "declaring victory" on the pollution issue. "I think that they've realized the easiest, cheapest path forward at this point, and they're not going to spend another dime trying to deal with the issue," Johnson said. The company operates four active steel-making coal mines in southeastern B.C. and says the operations support about 5,500 jobs. The company now claims its existing water treatment infrastructure can be used more efficiently, reducing the need for new plants. Elk Valley Resources says it has spent $2 billion on four treatment facilities that remove 95 to 99 per cent of selenium from the water they process. Its amended plan, dated June 18, 2026, proposes combining some treatment technologies and storing contaminated water in mine pits to handle periods of high water flow.
READ MORE: Calgary's Remova wins largest federal BECCS contract for Alberta carbon removal plant
READ MORE: Harvard study finds 400 largest U.S. data centres emit more than Denmark
The company's 2022 plan forecast treating 142 million litres of contaminated water daily by 2027. The new target is 135 million litres per day. Stannell said the four existing facilities currently treat 97.5 million litres daily. Simon Wiebe, a mining policy expert with Wildsight, said the most concerning changes involve cancelling treatment for the Fording River, the most contaminated waterway in the area.
"If they were to get the Fording River expansion project [approved], the water from that waste rock is going right into the Fording River as well," Wiebe said. The company is also applying to expand mining onto Castle Mountain, a 2,000-hectare area of traditional Ktunaxa territory. Stannell said the amended water plan does not account for these expansions, which would be reviewed in a separate environmental assessment. The B.C. Ministry of Environment and Parks declined to comment, citing the period between the recent provincial election and the swearing-in of a new cabinet. The province issued a ministerial order in 2013 requiring a strategy to stabilize and reverse contamination in the Elk Valley after pollution reached a regulatory tipping point. High levels of selenium, nitrate and sulphate were first detected in the Elk River in the 1990s.
With files from The Narwhal